2011 2012 Surface Treatments Phase 2
BID DATE
03/15/12 - 2:00
AGENCY
Town of Oro Valley
ESTIMATE
$750,000
SCOPE
The work to be performed includes, but is not limited to: thermoplastic paint removal, placing pavement preservation surface treatments (Stress Absorbing Membrane & CSS-1H fog seal), furnishing traffic control. The project also includes re-striping Silverton. The work is located in various subdivisions and streets including Pusch Ridge Estates, Desert Splendor Court, Sun City Vistoso Units 2, 3, 4, 5 & 6, Silverton, Rancho Vistoso NBH 7 Parcel C and K, Rancho Vistoso NBH 10 parcels G and P. All work is located within the Town of Oro Valley.