Access the Full Project by Clicking here!
Bidjugde
JOB
Ongoing Pipeline Replacement CIP WW26-12 IFB 26-21
BID DATE
12/1/26 - 4:00
AGENCY
Beaumont
ESTIMATE
n/a
SCOPE
Trenching and installation of approximately 400 linear feet of Schedule 80 PVC pipe connecting multiple force mains to existing air release valves in vaults at 2 locations on Berkshire Ave, installation of 8 new quarter-turn gate valves with covers and 8 new air release/vacuum combo valves serving the existing force mains, replacement of 4 existing copper pipe laterals at each location, pavement restoration, concrete collars around valve boxes and other incidental work. Locations: Berkshire Ave near the northwest corner of 1st Street, and Berkshire Ave near the northeast corner of Potrero Blvd. Contract time is 60 calendar days after procurement of long lead materials.
PREBID
11/5/2026 3:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT