Access the Full Project by Clicking here!
Bidjugde
JOB
Mt Veeder Road MPM 4 3 MPM 3 25
BID DATE
07/7/26 - 4:30
AGENCY
Napa County
ESTIMATE
n/a
SCOPE
Damage was caused to Mt. Veeder Road MPM 4.3 from the storm events occurring in Napa County in November 2025. Intense rainfall saturated the road embankment causing a downhill slide approximately 160 feet long on Mt. Veeder Road MPM 4.3 near Lokoya Road. The slide repair will include constructing a cast-in-drilled-hole (CIDH) concrete retaining wall extending approximately 187 feet. The wall heights are 4 feet to 16 feet. Tiebacks will be installed to provide additional lateral support and allow for one travel lane to remain open during construction. Repaving the roadway will restore the asphalt concrete surface and pre-slide drainage patterns. https://procurement.opengov.com/portal/countyofnapa/projects/265830

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT