Northside Sewer Phase 1
BID DATE
06/26/26 - 7:00
AGENCY
Del Rio
ESTIMATE
$6,900,000
SCOPE
Construction of approximately 1,940 LF of 33-inch and approximately 4,660 LF of 30-inch wastewater gravity mains by open cut and approximately thirty-one (31) manholes. The alignment includes a Union Pacific Railroad crossing which will require approximately 102 LF of 48-inch steel encasement by trenchless methods. The alignment begins at the Silver Lake WWTP and ends at Owens Dr. The project will include all pipes, manholes, encasements, lateral connections, surface restoration including pavement, testing, SWPPP measures, traffic control, and related material & procedures as outlined in the construction plans and specifications. https://www.civcastusa.com/project/6a040de967e9282cf72a1ea6/summary javier.esquivel@stvinc.com
PREBID
5/28/2026 7:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT