Bluebonnet Lane 8 Inch Sanitary Sewer
BID DATE
10/27/25 - 11:00
AGENCY
Red Oak
ESTIMATE
n/a
SCOPE
The project includes construction of approximately nine-hundred and thirty-two (932) linear feet of 8-inch sanitary sewer and seven (7) linear feet of 12-inch sanitary sewer. The sanitary sewer line begins at the end of Bluebonnet Lane, then proceeds west across Hickory Creek Drive, and continues along future alleyways before terminating at an existing gravity main. https://www.civcastusa.com/project/68e6807accb2d58d28a4b6e4/summary hunter.joseph@kimley-horn.com