South 212th Street Preservation 59th Place S 72nd Avenue S
BID DATE
09/30/25 - 8:00
AGENCY
Kent
ESTIMATE
$3,465,160
SCOPE
The project consists of placing HMA pavement on South 212th Street from about 59th Place S to 72nd Ave S in the Kent Valley. The work includes planing approximately 27,000 square yards of bituminous pavement at two-inch depth, planing roughly 7,600 square yards of bituminous pavement at six-inch depth, asphalt paving around 6,600 tons of HMA Cl ½”, PG 58V-22, reconstructing 14 curb ramps to ADA standards including pushbuttons, 121 vehicle detection loops, permanent channelization, around 530 square yards of sidewalk, tree removal and other work, all in accordance with the Contract Plans, Kent Special Provisions, and WSDOT Standard Specifications. https://www.kentwa.gov/Home/Components/RFP/RFP/1647/584