Vermont Avenue East Primary Sewer Rehabilitation Florence 83rd
BID DATE
05/7/25 - 7:00
AGENCY
Los Angeles
ESTIMATE
$5,595,131
SCOPE
In primary sewers along Vermont Avenue from 83rd St to Florence Ave ? Rehab 3,633 LF 27-in dia concrete brick sewer using CIPP lining method, including 23 LF along a curve ? Rehab 13 MHs, including: ?? Upsize frame & cover from 24-in to 30-in ?? 4 spot repairs ?? Repair 437 LF of concrete invert ? Construct 1 new 8-ft MH ? Also: ?? Traffic control ?? Sewer bypass, odor control, cleaning & CCTV https://www.rampla.org/s/opportunity-details?id=006Ql00000Kuxxx amado.carino@lacity.org