Aledo Road Infrastructure
BID DATE
02/13/25 - 2:00
AGENCY
Fort Worth
ESTIMATE
n/a
SCOPE
The major work will consist of approximately 4,750 linear feet of 16-inch water line installed using open cut method, with one bore crossing encased in approximately 80 linear feet of 30-inch steel, and 4,800 linear feet of variable diameter sewer main installed using open cut, with once bore crossing under Union Pacific Railroad for a length of approximately 155 linear feet of 30-inch steel. Water structure include gate valves, fire hydrants and one combination air valve. The sewer construction will occur within Aledo Road county ROW. https://fortworthtexas.bonfirehub.com/opportunities/168587