Keller Hicks Road Park Vista Boulevard Lauren Way
BID DATE
02/13/25 - 2:00
AGENCY
Fort Worth
ESTIMATE
n/a
SCOPE
The major work will consist of the (approximate) following: Removal of existing improvements and construction of three-lane 8” concrete pavement with curb and lime treated subgrade (16,400 SY), 4” concrete sidepath (56,000 SF), cast-in-place concrete retaining wall (1,700 SF), concrete box culvert with end treatments (10’x4’ RCB – 230 LF and 10’x6’ – 300 LF), storm drain line (various diameters – 2,900 LF), roadway illumination assemblies (14 EA), sanitary sewer line and appurtenances (8” – 200 LF and 18” – 90 LF), 12” water line and appurtenances (3,000 LF), pavement markings, signage, and traffic signal (1 EA) improvements. https://fortworthtexas.bonfirehub.com/opportunities/166472
PREBID
1/21/2025 2:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT