(CMAR) Granite Reef Wash Phase 2B Pima Park
BID DATE
11/4/24 - 12:00
AGENCY
Scottsdale
ESTIMATE
n/a
SCOPE
Granite Reef Wash Phase 2B (this project) has several sections. • 36” to 54” pipe from 82nd St to PIMA Park detention basins with a 42” detention basin bleed off pipe to Pima Road storm drain. o Excavates 2 large detention basins with significant large diameter piping in Pima Park • 60” to 90” pipe from Sheridan to Coronado Road in 87th Street. • 48” bleed off pipe in 87th Street from Coronado Road to McDowell Road. 96” Pipe, 10’x6’ Box and Channel from McDowell Road to McKellips Road and connection to the Phase 2A improvements which will be completed by summer of 2026. The Pima Park improvements include: • Eight or more Pickleball courts • Revised parking • Modified transit use • Modified trail system • Extensive landscaping emercado@scottsdaleaz.gov