CAN NOT CONFIRM BUDGET/CONTRACT AMOUNT. NOT YET AWARDED 3/31: UPDATE END OF MARCH: The first construction phase of this project will replace the two highest priority large valves near the intersection of McQueen and Pecos Roads. This project will also implement shutdown, dewatering, and startup plan, so the City and City’s Consultant may perform condition assessment of existing 48-in PCCP water pipeline, along Pecos Road between the Alma School Road and the Surface Water Treatment Plant (SWTP) east of McQueen Road, at 1475 E Pecos Road. Additional phases of construction for this project include installation, removal, and replacement of additional large and small valves and/or pipelines, shutdown, dewatering, and startup plans for additional pipeline segments.