Amburn Park Freeway Park Drainage Improvements
BID DATE
07/24/23 - 2:00
AGENCY
Galveston County
ESTIMATE
$4,650,000
SCOPE
This project involves the removal and replacement of approximately 9,200 SY of reinforced concrete pavement, removal and replacement of approximately 2,000 LF of 24” thru 48” storm sewer pipe, and installation of approximately 3,000 LF of 8” water line located in the Amburn Park Subdivision. This project also includes the removal and replacement of approximately 3,700 SY of reinforced concrete pavement, removal and replacement of approximately 1,400 LF of 24” thru 48” storm sewer pipe along with installation of 1,100 LF of 6’x4’ reinforced concrete boxes, and installation of approximately 3,250 LF of 8” water line and 400 LF of 8” sanitary sewer located in the Freeway Park Subdivision. https://www.civcastusa.com/project/649fa6a62d10118e00bd5693/summary john.rudloff@arkkengineers.com