Consolidated Canal Bridge Repair
BID DATE
01/8/15 - 9:00
AGENCY
Gilbert
ESTIMATE
$375,000
SCOPE
Construction work, in general, consists of repairing of the deck of the Baseline road Bridge over the Consolidated Canal by means of hydro demolition of delaminated and unsound concrete; placement of modified microsilica concrete overlay; construction of ADA-Compliant sidewalk ramps; reconstruction of settled pavement on the east approach to the bridge that includes roadway excavation, subgrade compaction, placement of controlled lowstrength material (CLSM) backfill, furnishing and placing aggregate base course and asphaltic concrete pavement; placing a penetrating concrete sealant; and placement of pavement markings. The Engineer’s estimate is $375,000 including the owner’s allowance. Ryan Blair, Project Manager E-mail: ryan.blair@gilbertaz.gov