Sanitary Sewer Rehabilitation Panoramic Way Area Phase III
BID DATE
12/16/14 - 2:00
AGENCY
Berkeley
ESTIMATE
$525,000
SCOPE
The work to be done consists of, but is not limited to, rehabilitation and construction of approximately 1,406 linear feet of 8-inch diameter sanitary sewer via pipe splitting (Method B), 20 linear feet of above ground steel encased 8-inch diameter sanitary sewer over an existing creek crossing, construction of manholes, manhole rehabilitation, excavation, replacement of approximately 1,020 linear feet of 4-inch and 6-inch diameter sewer laterals, and related work. Ronald V. Ranada, Jr., Associate Civil Engineer by email at rranada@cityofberkeley.info