Old Town Improv 1
BID DATE
03/22/23 - 2:00
AGENCY
San Diego
ESTIMATE
$3,340,000
SCOPE
This project consists of replacing 4,560 linear feet (0.87 miles) of 6, 8 and 10-inch AC Water Main Pipe with Polyvinyl Chloride (PVC) mains and abandon 596 linear feet of existing 6, 8-inch AC Water Mains, including appurtenances and services to the meter. The Scope of Work includes installing curb ramps and replacing driveways impacted by the curb ramp installation, repave approximately 4,842 linear feet (0.92 miles) of street surface by Asphalt Concrete Overlay and Slurry Seal. Brittany Friedenreich,619-533-3104,bfriedenreic@sandiego.gov https://pbsystem.planetbids.com/portal/17950/bo/bo-detail/102337#bidInformation