2023 Storm Drain Projects
BID DATE
01/31/23 - 2:00
AGENCY
Sandy
ESTIMATE
n/a
SCOPE
The 2023 Storm Drain Projects will include construction of the following four storm drain projects including storm drain, structures, dewatering, stream diversion, utility relocation, etc. Union Middle School Detention Basing Outlet - Outlet structures on two storm drain outfalls to the East Jordan Canal from the Union Middle School Detention Basin and improvements to the East Jordan Canal bank/channel. 671 West Storm Drain - Approximately 60 feet of 18-inch diameter RCP Storm Drain 700 West to Jordan River - Approximately 625 feet of 60-inch diameter RP from 700 West to the Jordan River. Bainbridge Storm Drain - Approximately 1,100 feet of 18-inch diameter RCP along Bainbridge Road.

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT