Bret Harte MS Main Water Line Replacement
BID DATE
09/1/22 - 2:00
AGENCY
Oakland
ESTIMATE
$250,000
SCOPE
The Scope of work consists of but is not limited to replacing form meter at the sidewalk, Approximately 350 of 4 of Old Rusted Galvanized Water Main Line through the Parking lot & Playground, up to Main Building. Method of replacement would be to open trench partial replacement on Sat & Sun only until the project is completed. Water to remain active during school operations. Reconnect all lateral supply lines to new main supply line. All open groundwork must be covered with metal plates after each and every work shift for safety concerns. Remove and discard all construction debris from the job site. mark.griggs@ousd.org https://www.ipdservices.com/clients/eastbay/?Oakland%20USD&Show=Planroom&Project=OUSD+70003+Bret+Harte+MS+Main+Water+Line+Replacement
PREBID
8/26/2022 2:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT