(CMAR) Santan Water Treatment Plant Phase II
BID DATE
03/16/15 - 1:00
AGENCY
Gilbert
ESTIMATE
$82,808,000
SCOPE
INTERVIEWS END OF FEB, AWARD 2ND WEEK MARCH: GILBERT and CHANDLER intend to construct a 24 MGD expansion to the Santan Vista Water Treatment Plant. Construction must be complete by January 2018. The Preliminary Project Description is attached. There will be a single final list of at least three and not more than five firms. One contract may be awarded. One firm may be awarded the contract. This will be a Construction Manager at Risk (CMAR) Project pursuant to ARS Section 34-601 et seq. A general description of the Project is: The Santan Vista Water Treatment Plant – Phase II expansion which is a buildout condition for the facility that will expand the capacity from 24 MGD to 48 MGD Gregory.Smith@gilbertaz.gov

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT