Access the Full Project by Clicking here!
Bidjugde
JOB
Gollihar Rd Greenwood Dr Crosstown Expressway Bond 2018
BID DATE
07/20/22 - 2:00
AGENCY
Corpus Christi
ESTIMATE
n/a
SCOPE
The project scope of improvements includes the complete reconstruction of Gollihar Road from Greenwood Drive to Crosstown Expressway, a distance of 3,900’. In addition to surface improvements, the project includes stormwater, water, wastewater, and gas infrastructure improvements. The existing roadway will be demolished and rebuilt with new pavement, curb and gutter, sidewalks, ADA compliant curb ramps, signage, pavement markings, RTA improvements, street light improvements, and traffic and pedestrian signal improvements. Stormwater improvements include the replacement of all curb inlets, deficient reinforced concrete pipes and concrete structures, and all corrugated metal pipes. Water improvements include the replacement of the existing 12” asbestos concrete pipe (ACP) with 12” C900 PVC. Wastewater improvements include approximately 1,725 LF of wastewater pipebursting from the upstream end east of Falkinson to the downstream end just east of Bernandino. Additionally, the scope of wastewater improvements includes removal of an existing wastewater manhole, rehab of eight (8) existing wastewater manholes with fiberglass liners, installation of new 8” SDR 26 PVC wastewater line, and installation of a steel cased wastewater line though a storm junction box. Wastewater improvements include the replacement of the existing wastewater line crossing Gollihar at about mid-Project Limits. Gas infrastructure improvements include conflict resolution and installation of a new 8” gas line from Greenwood to Crosstown Expressway, to be installed by the City’s gas department. Contractor shall perform all utility improvements and upgrades thru related coordination with the City and private utility owners. Two pavement options will be considered, Base Bid 1 Hot Mix, Asphalt (HMAC) and Base Bid 2 Concrete Pavement. Contractors may bid either one or both options, all in accordance with the project specifications and plans. https://www.civcastusa.com/project/628255c80b7f2c392440811f/summary LoisH@cctexas.com
UPDATES