State St North Temple Reconnect Main
BID DATE
02/11/22 - 2:00
AGENCY
Salt Lake
ESTIMATE
$3,023,000
SCOPE
Installation of 2,000 LF of 12” PVC C900 waterlines at the location listed above. Installation of the waterlines will include looping underneath a 60” storm drain in the intersection of North Temple and State Street. Existing services will need to be reconnected to the new waterlines and existing residential water meters replaced with new water meters. Isolation valves and system valves will be installed at locations indicated on the drawings. Sewer rehabilitation work will also be done in the same area as the water replacement, including point repairs in previously lined 8” CIPP pipe along State Street, along with 950’ of new CIPP lining in 8” sewer lines in Hillside and 200 North. Kevin Kranendonk +801 (483) 6841 kevin.kranendonk@slcgov.com
PREBID
1/27/2022 2:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT