North McKinney Parallel Interceptor
BID DATE
01/18/22 - 2:00
AGENCY
Wylie
ESTIMATE
$12,530,000
SCOPE
This project includes construction of approximately 820 linear feet of 48” sewer line, 155 linear feet of 48” sewer line by bore with 66” steel casing, 7,881 linear feet of 54” sewer line, 2,228 linear feet of 66” sewer line, 460 linear feet of 66” sewer line with 84” steel casing installed by open cut, tee base manholes, connections to existing sewer lines, erosion and sedimentation control, dewatering, and associated site restoration and improvements. The project also includes installation of 11,765 linear feet of 4" PVC conduit, 1.66" HDPE innerduct, and fiber optic cable. Lastly, the project also includes the installation of approximately 7,140 linear feet of 5-strand barbed wire fencing. https://www.civcastusa.com/project/61b82657594c2950ff7c73cc/summary jwalton@tnpinc.com
PREBID
1/4/2022 10:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT