Access the Full Project by Clicking here!
Bidjugde
JOB
Village Westpointe Subdivision Section 1
BID DATE
11/9/21 - 2:00
AGENCY
Waterstone Development Group
ESTIMATE
n/a
SCOPE
The work generally consists of approximately 15,350 cubic yards of concrete pavement with curb on 6" lime stabilized subgrade; 5,642 feet of 8" or 10" waterline, waterline with valves, fittings, service lines and fire hydrants, 4,365 feet of saintary sewer lines with manholes and service lines; 2,750 feet of reinforce concete storm sewer pipe from 18" to 6' x 4' box culverts with inlets, junction boxes, manholes and safety end treatments; 36,500 cubic yards of roadway, channel and detention pond excavation; and other items of work a detailed in the plans. https://www.civcastusa.com/project/616f352c95a6a89832778e2f/summary msauceda@bakerlawson.com

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT