Access the Full Project by Clicking here!
Bidjugde
JOB
(PREQUAL) Vineyard City Phase 1 Water Distribution Pipeline
BID DATE
10/25/21 - 2:00
AGENCY
Vineyard
ESTIMATE
n/a
SCOPE
The Work of this Contract includes the installation of 12-inch, 16- inch, 24-inch, 30-inch, and 36-inch DR-18 C-900 PVC piping, valves, and appurtenances; installation of 28-inch steel casing and 20-inch DR-11 HDPE carrier pipe by means of jacking and boring; installation of 36-inch steel casing and 28-inch DR-11 HDPE carrier pipe by means of jacking and boring; installation of 24-inch RCP; construction of a concrete headwall; crossing of UTA and UPRR railroad tracks at three locations - two by means of jacking and boring, and one through an existing concrete tunnel; water service connections; installation of new fire hydrants; removal of existing concrete vaults and their associated piping, valves, and appurtenances; and capping and abandoning existing waterlines.

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT