Goshen Town Spring Improvements
BID DATE
06/3/21 - 2:00
AGENCY
Goshen
ESTIMATE
n/a
SCOPE
Project includes constructing a new cutoff wall in the spring tunnel, a new spring overflow line, a new high overflow line by coring through bedrock near the tunnel entrance, a new concrete metering vault, new spring supply line inlet piping, and an airgap structure at the tank site with interconnect piping and drain line. The project will be performed in two phases. The first phase will include the tank site improvements and will commence upon receipt of Notice to Proceed. The second phase will include the spring site improvements www.sunrise-eng.com