JOB
LVMWD CMWD Interconnection
BID DATE
05/25/21 - 2:00
AGENCY
Calleguas Municipal WD
ESTIMATE
$18,083,500
SCOPE
These improvements include (but are not limited to): construction of an underground concrete structure Pump Station / Pressure Regulating Station (“PS/PRS”) including two vertical turbine pumps with 400 horsepower motors, suction and discharge piping and appurtenances, pressure regulating station, metering facilities, electrical facilities, two 500kW portable diesel standby generator sets, and related equipment; 30 inch diameter pipeline extending from the PS/PRS to Lindero Feeder No. 2; modifications to the existing Falling Star Meter Station and construction of a new metering station (TWSD Meter Station); and modifications to several existing air release and vacuum valves located along Lindero Feeder No. 2; and modifications to piping at Lindero Pump Station #1 (LPS1).
UPDATES