Arrowhead Water Production Facility Rehabilitation Pecos Surface Water Treatment Plant Surge System
BID DATE
03/9/21 - 2:00 LIVE!
AGENCY
Chandler
ESTIMATE
$8,000,000
SCOPE
MGC Base: $7,274,170 Alt: $200,000 Redpoint Base: $8,531,240 Alt: $168,655 Filanc Base: $6,190,000 Alt: $86,837 FPS Base: $7,395,267 Alt: $167,355 Achen Gard Base: $6,053,000 Alt: $45,000 PCL Base: $6,706,328 Alt: $60,000 Garney Base: $6,084,000 Alt: $55,000 Work under this contract includes: Construction for the rehabilitation of the Arrowhead Water Production Facility and approximately 2,400 feet of waterline replacement, and the installation of a surge tank at the Pecos Surface Water Treatment Plant. Work must be completed within 365 consecutive calendar days from the Notice to Proceed. The Engineer’s Estimate range is $ 7.5 million - $ 8 million. paula.brown@chandleraz.gov