Access the Full Project by Clicking here!
Bidjugde
JOB
State Route 69 16 inch Water Pipeline (REBID)
BID DATE
04/29/21 - 2:00
AGENCY
Prescott
ESTIMATE
$675,000
SCOPE
ORG RESULTS: Mountain High Excavating - $665,864 Fann Contracting - $874,730 Capital Improvements - $888,888 The project generally consists of the construction of a new 16-inch waterline paralleling the northern side of State Route 69 from the western edge of Holiday Drive to the UHaul Store. The existing line servicing this area will be partially removed and abandoned and new water service lines and water main stubs will be constructed off the 16-inch line to service future development david.bradley@prescott-az.gov
UPDATES