Cherry Avenue Drainage Improvements
BID DATE
01/27/11 - 3:00
AGENCY
City of Flagstaff
ESTIMATE
$625,000
SCOPE
The proposed drainage design requires abandoning-in-place several sections of storm drain between Cherry and Bonito and constructing a storm drain system adequately sized to carry the runoff. Construction of the storm drain system will include catch basins, manholes, and headwalls as called out on the plans. There are several places where waterline conflicts exist and vertical adjustments of the existing waterlines will be required. Due to shallow cover over the storm drain on Cherry, a concrete cap will be installed per the plans. The construction will include construction of a channel between Aztec and Mogollon Streets and a retention area at the intersection of Thorpe and Cherry