Tortolita Road Sidewalk
BID DATE
09/3/20 - 3:00
AGENCY
Marana
ESTIMATE
n/a
SCOPE
The Tortolita sidewalk infill improvements consist of installing approximately 1,100 LF of curb and 6’ wide sidewalk along Tortolita Road connecting two previously completed sidewalk sections. The Sidewalk will include new ramps and Tekway (terra cotta) tiles at the returns. Two new driveway aprons with post barricades will be added to the project along with one new asphalt driveway. Rudy Torres (520) 382-1983 rtorres@maranaaz.gov