South Whittier Outfall Relief Trunk Sewer Rehabilitation Phase 4
BID DATE
02/4/20 - 2:00
AGENCY
Sanitation District Los Angeles
ESTIMATE
$1,900,000
SCOPE
The project will rehabilitate two siphons consisting of approximately 83 feet of 54-inch diameter reinforced concrete pipe on the South Whittier Outfall Trunk Sewer with cured-in-place pipe (CIPP) liner and approximately 19 feet of 48-inch diameter reinforced concrete pipe on the South Whittier Outfall Relief Trunk Sewer with reinforced concrete top encasement. The project will also rehabilitate two (2) structures and one (1) manhole with epoxy coating system. The first siphon is in private property located adjacent to the intersection of Excelsior Drive and Shoemaker Avenue in the City of Santa Fe Springs. The second siphon is located at the intersection of Carmenita Road and Rosecrans Avenue

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT