2019 Water Main Replacement Monte Rosa Drive
BID DATE
10/30/19 - 2:00
AGENCY
Menlo Park
ESTIMATE
n/a
SCOPE
The scope of work on Monte Rosa Dr., Sharon Road, Deanna Dr., and La Entrada Middle School includes abandoning existing 12-inch asbestos cement pipe (ACP) water mains and installing 1,211 linear feet of 12-inch ductile iron pipe (DIP) water main, 477 linear feet of 2-inch Schedule 80 polyvinyl chloride (PVC), 477 linear feet of 4-inch PVC, nine residential services, one irrigation service, two backflow preventers, and one fire hydrant. The scope includes other incidentals as necessary to complete the work as shown on the plans and as specified in the Special Provisions. faheydari@menlopark.org