North Valley Landfill Cell 2 Liner Installation
BID DATE
06/26/19 - 2:00
AGENCY
Logan
ESTIMATE
n/a
SCOPE
1 Place drain-net on north side of existing access road sf 34,200 2 Remove and replace existing access road soils onto drain net yd3 1,900 3 Cell 2 Excavation and Grading yd3 28,300 4 Prepare Subgrade acres 7 5 Excavate and Backfill Anchor Trench ft 1,150 6 Expose Existing Liner ft 1,150 7 Install Reinforced GCL sf 306,000 8 Install Textured 60-mil HDPE Liner sf 306,000 9 Place 8 Oz. Needle Punch Geotextile yd2 3,700 10 Place 8” Diameter DR 11 Perforated HDPE Pipe ft 1,850 11 Install Drain Net sf 306,000 12 Place Gravel Backfill yd3 550 13 Place Cover Soil yd3 3,200 14 Place Slag yd3 3,555 tyler.richards@loganutah.org lori.mathys@loganutah.org
PREBID
6/18/2019 10:00