JOB
Inter Garrison Road Water Distribution Pipeline
BID DATE
06/27/19 - 2:00
AGENCY
Marina Coast WD
ESTIMATE
$675,000
SCOPE
Install approximately 1,700 linear feet of new 18-inch ductile iron pipe (DIP) water main in Inter-Garrison Road, from approximately 2,000’ east of Shoonover Road to approximately 500’ west of the intersection with Sherman Blvd. in East Garrison. The new main will connect to existing 12” water mains at both its eastern and western ends. This work includes all associated fittings, valves, appurtenances, pavement removal and restoration, reconnecting existing mains and services along these pipes, and abandonment grouting of existing water mains within the right-of-way. Stephenie Verduzco: sverduzco@mcwd.org Cc. Andrew Racz: aracz@mcwd.org
PREBID
6/13/2019 11:00

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT