Flap Gate Replacement
BID DATE
04/4/19 - 2:30
AGENCY
Clifton
ESTIMATE
$95,000
SCOPE
To allow drainage from the Town to the San Francisco River there are a series of drains which penetrate the flood walls. To prevent water from back flowing through the drains during high flows in the San Francisco River, the drains are equipped with either slide or flap gates on the downstream, or river side, of the flood walls. This project entails the removal of the existing flap and slide gates and the installation of flap gates, according to the construction plans, specifications, and manufacturer's recommended installation specifications. All project gates are located north of the Highway 191 bridge along the San Francisco River. The Town of Clifton has a budget of $95,000 allotted for this project. There is a total of 13 gates included in this project. dpowell@bowmanconsulting.com