Mutton Hollow 50 East Street Rebuild
BID DATE
07/17/18 - 10:00
AGENCY
Davis County
ESTIMATE
n/a
SCOPE
Davis County is in need of reconstructing Mutton Hollow Road and 50 East in the Mutton Hollow Township. The project will include replacement of asphalt, 8 inches of road base, some storm drain modification, pedestrian ramp replacements, replacement of select sections of curb and gutter and replacement of drive approaches as needed. The Mutton Hollow Road section to be replaced is approximately 3100 feet long by 40 feet wide. The 50 East section is approximately 1600 feet long by 30 feet wide. Construction on the project will take place this July – August. We will be following Mutton Hollow Water District’s replacement of their water line. Construction is anticipated to start on Mutton Hollow Road the middle of July and 50 East the middle of August. Dax Teuscher +1 801-451-3492 dteuscher@co.davis.ut.us