Access the Full Project by Clicking here!
Bidjugde
JOB
Sells Big Fields Transmission Main Replacement Project 418 23W
BID DATE
07/3/18 - 2:00
AGENCY
TOUA
ESTIMATE
$5,000,000
SCOPE
B TOTAL LISTED IN BID RESULTS, A&B BIDS AS FOLLOWS: T&T Construction $2,687,547.50 $2,638,533.50 Pimmex/Blucor $5,225,000.00 $5,141,000.00 Show Low Construction No Bid No Bid Team Fishel $3,472,207.53 $3,354,183.76 Central Arizona Civil Construction $3,306,049.00 $3,225,137.00 EMC No Bid No Bid Redpoint Contracting No Bid $2,567,272.00 Sellers & Sons $2,709,988.25 $2,624,602.75 Granite Construction $3,469,764.26 $3,466,593.00 Meridian No Bid No Bid MD Merrett $3,483,257.15 $3,399,357.15 Fortis No Bid No Bid Arrow Indian Contractors No Bid No Bid; Water main through Sells, AZ. Ross.Schroeder@hq.toua.net
UPDATES