Sanitary Sewer Force Main Rehabilitation (REBID)
BID DATE
11/29/18 - 2:00
AGENCY
Foster City
ESTIMATE
$663,000
SCOPE
JMB Construction - $1,144,161 The Sanitary Sewer Force Main Rehabilitation Project (CIP 455-661) consists of rehabilitation of an asbestos cement pipe by sliplining with new liner pipe, construction of new and replacement polymer concrete manholes, installation of new isolation valves, temporary flow bypassing and traffic control, surface restoration, and associated work.