Tracy Hills Pump Station JJWTP
BID DATE
11/1/17 - 2:00
AGENCY
Tracy
ESTIMATE
n/a
SCOPE
In general, the work to be done consists of construction of a 5.3 million gallon per day (mgd), 3,670 gpm, booster pump station and 10,000 gallon surge tank to serve the proposed Tracy Hills Zone 3; two (2) concrete cores, approximately 28-inch diameter; a 24-inch and 30-inch diameter ductile iron pump suction pipeline; an electrical and control building; on-site 750 KW emergency generator with integral base fuel storage tank and fuel; new electrical service and transformer pad, and all associated piping, valves and appurtenances and all other incidentals not specifically listed under another schedule, but required for a complete installation, complete in place, tested, and ready for operation.

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT