Water Main Rehabilitation ABB: 12th Street to 16th Street & Roosevelt Street to McDowell Road
BID DATE
12/11/12 - 2:00 LIVE!
AGENCY
City of Phoenix
ESTIMATE
$875,000
SCOPE
The Water Main Rehabilitation work will include approximately 7805 LF of 6-inch pipe rehabilitation (cleaning and lining) and 1,163 LF of 8-inch pipe rehabilitation (cleaning and lining), 17936 temporary bypass piping, 284 SY of Subgrade Preparation; 59 Tons Asphalt Concrete; and various other miscellaneous items. This project has a 2% SBE goal. The Engineer's Estimate is $793K to $970K. For questions related to this project contact Kandi Kawolsky at (602) 534-8352.

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT