Lone Butte WWTP Headworks Improvements
BID DATE
05/23/17 - 3:35 REAL-TIME
AGENCY
Chandler
ESTIMATE
n/a
SCOPE
CHANGED BID DATE BIDS DUE 5/22, OPEN 5/23. Work under this contract includes: replacing the existing Bar Screen and Washer/Compactor, including associated appurtenances, at the Lone Butte Waste Water Treatment Plant. Work also includes electrical and instrumentation such as the installation of a Local Control Panel, a Motor Control Panel, an ultrasonic level sensor/transmitter, the replacement of power duct banks and conductors and associated programming as outlined in the Contract Documents. Work also includes replacement of a yard hydrant and associated piping, yard piping and miscellaneous site work. Lone Butte Waste Water Treatment Plant will continue to operate during the replacement of the equipment. hafiz.noor@chandleraz.gov