Perris Boulevard Widening
BID DATE
05/10/17 - 3:00
AGENCY
Perris
ESTIMATE
$4,500,000
SCOPE
In general, this street widening project for Perris Boulevard and San Jacinto Avenue, provides additional travel lanes and turning lanes from 4th Street to the I-215 Bridge. The construction is adjacent to the County library, City Hall, and a City park. The construction items include standard and specialty installation work for AC paving, aggregate base, curb and gutter, PCC sidewalk , storm drain items, City sewer line replacement, AC, colored textured sidewalk replacement at Library, decorative streetlights, bio-retention basins construction and other work to complete the upgrade improvements for the Citys campus. The new construction will require much demolition, including removal of property fencing, concrete block property walls, the removal of over 34 trees, existing curbs, and sidewalks.

TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT