Access the Full Project by Clicking here!
Bidjugde
JOB
REBID-Goodyear Airport Taxiway Alpha Lighting & Signage Modification
BID DATE
01/15/13 - 2:00 LIVE!
AGENCY
City of Phoenix
ESTIMATE
$1,150,000
SCOPE
ORG BID RESULTS: Rural Electric Inc. - $979,471 CS Construction Inc. - $1,019,997 Royal Southwest Electric Co. - $1,184,967 AJP Electric, Inc. - $1,199,884 Corbins Electric - $1,295,702 This project will include relocation of existing hold bars and mandatory signs to 260’ from the runway centerline, installation of runway guard lights at various Taxiway Alpha intersections, pavement striping and layout, drainage, electrical, runway lighting adjustment and signs. This is a federal-aid project. This project has a 1.5% DBE availability. The Engineer's Estimate is $1.0 Million to $1.3 Million.

PRE-BID
1343664000 REC
TRACKING
DOCUMENTS
PHOLDERS
LOCATION
ABSTRACT