BidJudge.com - Projects
  • Onyx Paving Co
  • 2026
  • 135
  • 26
  • 19.26%
  • $55,277,999
  • 5.21%
  • 17.96%
  • 9.06%
  • $305,485,669
2890 E La Cresta Ave
Anaheim CA
92806
714-632-6699
Health Breakdown
Avg Left
20
Success
30
Avg Avg
10
Year Proj
-5
2 Year Prior Proj
-5
Qual Based
0
Cash Flow
-15
 
35%
35%
Health
Financial Health & Pipeline Brief
Analyzed On:  Aug 13, 2026
Onyx Paving Co (Powered by Grok AI)
Near-term Outlook (next 3-6 months)
Onyx Paving Co enters the period with **$25M** in remaining backlog from 2026 awards, including **$6.6M** on the **$9.7M** FY25-26 Pavement Rehabilitation and **$2.5M** on Local Street Preventative Maintenance. Multiple projects bid in May-July 2026 with 85-120 month durations will generate steady progress billings, supporting positive cash flow assuming typical 5.3-5.8% margins on low bids.

Medium-term Outlook (6-12 months)
Annual win volume of **$50M-$65M** at a 19.5-20.3% success rate on **$274M** bids should replenish backlog as current long-duration projects advance. The **$25M** active backlog provides a solid base, but conversion of new awards into executed contracts will determine revenue stability through 2027.

Key Risk Period
Extended 70-120 month contract durations on the majority of the **$25M** backlog create exposure to delayed payments and cost escalation beyond the next 12 months. Cash flow pressure may intensify if progress billings lag on the largest remaining items such as the **$4.6M** Local Street Rehabilitation and **$3.2M** Newhope Street project.

Recommendations
Prioritize acceleration of billing cycles on long-duration contracts and maintain bidding volume above **$270M** annually to sustain **$50M+** annual awards. Implement monthly backlog burn-rate tracking to identify margin erosion early.
 
JOBS LOW
  • FY 2026 27 Residential Roadway Rehabilitation
  • Placentia
  • 8/27/26
  • 2025 2026 CDBG Street Improvements Randolph Street Improvements
  • Riverside
  • 8/20/26
  • Residential Resurfacing Phase II Paving Improvements
  • Azusa
  • 8/5/26
  • Rehabilitation Resurfacing Newhope Street Ward Street Ellis Avenue Slater Avenue
  • Fountain Valley
  • 7/23/26
  • Local Street Rehabilitation Zones 5 6 CIP 7944
  • Norwalk
  • 7/15/26
  • Candlewood Area Street Rehabilitation
  • Fullerton
  • 7/2/26
  • Raymond Avenue Rehabilitation
  • Fullerton
  • 6/3/26
  • Fiscal Year 2025 26 2026 27 Street Improvements
  • Agoura Hills
  • 5/26/26
  • Highway Safety Improvement Program HSIP Traffic Calming
  • Artesia
  • 5/21/26
  • Local Street Preventative Maintenance FY 25 26
  • Santa Ana
  • 5/21/26
  • Residential Roadway Rehabilitation 26002 Quadrant B4
  • Fountain Valley
  • 5/13/26
  • FY25 26 Pavement Rehabilitation
  • Oceanside
  • 5/6/26
  • Curb Gutter Sidewalk Replacement CP60000030
  • Simi Valley
  • 5/5/26
  • Palm Street Area Rehabilitation
  • Fullerton
  • 3/26/26
  • First Avenue Rehabilitation
  • Arcadia
  • 3/26/26
  • Street Preservation Local Citywide FY 25 26 Worktag 68598
  • Pomona
  • 3/16/26
  • Los Alisos Pavement Rehab
  • Rancho Santa Margarita
  • 3/5/26
  • Santa Margarita Parkway Pavement Rehab
  • Rancho Santa Margarita
  • 3/5/26
  • Blake Street Other Roads Phase 1
  • San Bernardino County
  • 3/5/26
  • Business Area Road Improvements
  • Santa Ana
  • 2/25/26
  • FY 25 26 Street Rehabilitation
  • Duarte
  • 2/23/26
  • E Santa Fe Parking Lot Rehabilitation
  • Fullerton
  • 2/12/26
  • Street Pavement Repair Program FY 2025 26
  • Newport Beach
  • 2/10/26
  • FY24 25 Residential Street Rehabilitation
  • West Covina
  • 2/9/26
  • FY 2025 26 Annual Minor Streets Rehabilitation Program CDBG
  • Simi Valley
  • 1/22/26
  • Commercial Street Improvement DInard Ave Maryton Ave Marquardt Ave Park Street Pike St
  • Santa Fe Springs
  • 1/22/26
Bidjudge
JOBS BID
  • FY 2026 27 Arteral Roadway Rehabilitation
  • Placentia
  • $1,388,000
  • 8/28/26
  • SB1 Citywide Pavement Rehabilitation CIP 2511
  • Hemet
  • $2,408,000
  • 8/27/26
  • FY 2026 27 Residential Roadway Rehabilitation
  • Placentia
  • $2,015,000
  • 8/27/26
  • CDBG Funded Grind Overlay FY27
  • Glendora
  • $366,000
  • 8/27/26
  • Bay Ave Sidewalk Improvements CDBG Fiscal Year 24 25
  • Moreno Valley
  • $1,773,000
  • 8/26/26
  • NO 1753 University Drive Pavement Rehabilitation Avalon Blvd Wilmington Ave
  • Carson
  • $4,567,000
  • 8/24/26
  • 2025 2026 CDBG Street Improvements Randolph Street Improvements
  • Riverside
  • $3,369,000
  • 8/20/26
  • Avenida De Platina Pavement Rehab Invitation Bid
  • Coachella
  • $345,000
  • 8/19/26
  • Gillet Road Rehabilitation
  • El Centro
  • $684,000
  • 8/13/26
  • South Glendale Pavement Management Plan PMP
  • Glendale - CA
  • $10,907,000
  • 8/12/26
  • Landau Boulevard Public Alley Reconstruction
  • Cathedral City
  • $846,000
  • 8/11/26
  • Main St Parking Lots Resurfacing Restriping
  • Santa Ana
  • $406,000
  • 8/7/26
  • Riverside Drive
  • San Bernardino County
  • $3,067,000
  • 8/6/26
  • CP26 405 Bob Hope Pavement Rehab
  • Rancho Mirage
  • $466,000
  • 8/5/26
  • Residential Resurfacing Phase II Paving Improvements
  • Azusa
  • $848,000
  • 8/5/26
  • 2026 Pavement Overlay CIP No ST022
  • San Marcos - CA
  • $2,263,000
  • 8/4/26
  • Jefferson Avenue Clinton Keith Road Pavement Rehabilitation
  • Murrieta
  • $6,370,000
  • 7/30/26
  • FY27 CDBG Street Resurfacing ADA Improvement
  • Pasadena - CA
  • $1,172,000
  • 7/30/26
  • Peyton Drive Pavement Rehabilitation
  • Chino Hills
  • $2,334,000
  • 7/30/26
  • Carmenita Road Rehabilitation 550 North Excelsior Drive Rosecrans Avenue CIP 7184
  • Norwalk
  • $3,369,000
  • 7/29/26
  • Vista Way FHWA Overlay
  • Oceanside
  • $1,283,000
  • 7/28/26
  • Rehabilitation Resurfacing Newhope Street Ward Street Ellis Avenue Slater Avenue
  • Fountain Valley
  • $3,169,000
  • 7/23/26
  • 2025 26 Citywide Residential Overlay
  • Westminster
  • $3,269,000
  • 7/23/26
  • 2024 06 Citywide Misc Concrete Improvements
  • La Quinta
  • $111,000
  • 7/23/26
  • FY 2026 27 Annual Major Streets Rehabilitation Program Los Angeles Avenue First Street Erringer Roa
  • Simi Valley
  • $2,122,000
  • 7/21/26
  • 1st Street Improvements Ramona Blvd San Jacinto Ave SJ 565
  • San Jacinto
  • $277,888
  • 7/21/26
  • Residential Streets Rehabilitation Zone 3 Phase II
  • Rialto
  • $2,182,000
  • 7/16/26
  • Residential Streets Rehabilitation Zone 3 Phase 1
  • Rialto
  • $1,535,000
  • 7/15/26
  • Local Street Rehabilitation Zones 5 6 CIP 7944
  • Norwalk
  • $4,636,000
  • 7/15/26
  • City Wide Curb Gutter Sidewalk ADA Ramps Repair Delano Drive Sidewalk Improvements
  • Riverside
  • $1,173,888
  • 7/14/26
  • Alondra Blvd Pavement Rehabilitation Studebaker Rd Gridley Rd CIP 7921
  • Norwalk
  • $2,373,000
  • 7/14/26
  • Asphalt Concrete Maintenance Services
  • Orange County
  • $3,553,000
  • 7/10/26
  • West Side Road Repairs
  • Paso Robles
  • $3,323,000
  • 7/9/26
  • IFB 2026 08 Construction Street Rehabilitation Districts 2 3 Phase I
  • Pomona
  • $888,000
  • 7/7/26
  • Citywide Improvements
  • Perris
  • $7,852,000
  • 7/7/26
  • Candlewood Area Street Rehabilitation
  • Fullerton
  • $622,000
  • 7/2/26
  • Tajiguas Access Road Extension Site Improvements 2026
  • Santa Barbara County
  • $1,308,726
  • 7/2/26
  • 2025 26 Pavement Rehabilitation CIP 2516
  • Hemet
  • $616,667
  • 6/30/26
  • Citywide Resurfacing Reconstruction CIP 50106
  • Pico Rivera
  • $9,136,999
  • 6/30/26
  • Harbor Blvd Street Rehabilitation
  • Fullerton
  • $1,199,000
  • 6/30/26
  • Residential Resurfacing Phase I Concrete Improvements
  • Azusa
  • $616,677
  • 6/25/26
  • Pavement Rehabilitation Lawton Avenue New Jersey Street Prospect Avenue CIP 26 133
  • Loma Linda
  • $784,500
  • 6/24/26
  • Neighborhood Street Resurfacing Cal Gisler
  • Oxnard
  • $3,737,000
  • 6/23/26
  • Safe Routes School Placerita Junior High School Hart High School
  • Santa Clarita
  • $1,111,000
  • 6/22/26
  • Apple Street Improvements
  • Oceanside
  • $844,667
  • 6/22/26
  • 2026 Annual Street Maintenance
  • Malibu
  • $1,067,000
  • 6/18/26
  • South Palm Canyon Road Reconfiguration
  • Palm Springs
  • $2,877,000
  • 6/18/26
  • Air Expressway Pavement Rehabilitation
  • Adelanto
  • $3,311,550
  • 6/16/26
  • FY 2026 27 Annual Major Streets Rehabilitation Program Alamo St Erringer Rd Gage Ave CP60000018
  • Simi Valley
  • $698,879
  • 6/16/26
  • Citrus Redlands Connectivity
  • Perris
  • $630,325
  • 6/15/26
  • Cedar Street Rehabilitation Occidental Street Edinger Avenue
  • Santa Ana
  • $422,740
  • 6/11/26
  • ST260 Pavement Improvements Zone 1 Cypress Avenue
  • Chino
  • $1,041,370
  • 6/11/26
  • Knott Avenue Lincoln Avenue Artesia Boulevard 8th Street Rehabilitation
  • Buena Park
  • $5,727,000
  • 6/8/26
  • McFadden Ave Phase I Brookhurst St Bolsa Ave Phase II Street Improvement
  • Westminster
  • $3,737,000
  • 6/3/26
  • Raymond Avenue Rehabilitation
  • Fullerton
  • $1,414,000
  • 6/3/26
  • 2026 Residential Streets Rehabilitation
  • Garden Grove
  • $727,000
  • 6/2/26
  • 2026 Fall Pavement Rehabilitation
  • Ontario
  • $4,282,000
  • 6/1/26
  • 2025 26 CDBG Infrastructure Improvements
  • Alhambra
  • $747,000
  • 5/28/26
  • Fiscal Year 2025 26 2026 27 Street Improvements
  • Agoura Hills
  • $1,007,000
  • 5/26/26
  • Highway Safety Improvement Program HSIP Traffic Calming
  • Artesia
  • $793,000
  • 5/21/26
  • Local Street Preventative Maintenance FY 25 26
  • Santa Ana
  • $3,369,000
  • 5/21/26
  • Citywide Slurry Seal Roadway Maintenance Program 2026
  • Santee
  • $1,074,631
  • 5/21/26
  • A Street Corridor Safety Improvements HSIPSL 5198 029
  • Perris
  • $594,505
  • 5/20/26
  • Sunny Hills Twilight E Las Palmas Area Street Rehabilitation
  • Fullerton
  • $2,687,000
  • 5/19/26
  • 2025 2026 Pavement Rehabilitation
  • Arcadia
  • $1,282,000
  • 5/19/26
  • Citywide Sidewalk Reconstruction 3
  • Fontana
  • $936,000
  • 5/18/26
  • Rehabilitation Resurfacing Euclid St Slater Ave Talbert Ave Talbert Ave Brookurst St Bushard St
  • Fountain Valley
  • $2,844,000
  • 5/14/26
  • FY 2025 26 Annual Minor Streets Rehabilitation Program Phase II Asphalt
  • Simi Valley
  • $2,122,000
  • 5/14/26
  • Pauba Road Pavement Rehabilitation
  • Temecula
  • $2,181,220
  • 5/14/26
  • Residential Roadway Rehabilitation 26002 Quadrant B4
  • Fountain Valley
  • $2,317,000
  • 5/13/26
  • FY2026 Street Rehabilitation
  • West Hollywood
  • $1,617,000
  • 5/7/26
  • FY25 26 Pavement Rehabilitation
  • Oceanside
  • $9,669,000
  • 5/6/26
  • Curb Gutter Sidewalk Replacement CP60000030
  • Simi Valley
  • $276,000
  • 5/5/26
  • Residential Streets Improvement Monterrey Baker Group 19
  • Anaheim
  • $8,273,000
  • 4/30/26
  • FY 25 26 Citywide Street Slurry Seal Asphalt Repair
  • Duarte
  • $209,459
  • 4/30/26
  • Slurry Seal 2026 CIP Nos 8262 8313
  • Vista
  • $3,205,038
  • 4/28/26
  • Citywide Pavement Repair Rehabilitation Program 2026
  • Santee
  • $1,989,612
  • 4/28/26
  • Miles Avenue Pavement Rehabilitation
  • La Quinta
  • $3,250,751
  • 4/23/26
  • Citywide Pavement Rehabilitation Program Fiscal Year FY 2025 26
  • Moreno Valley
  • $6,139,000
  • 4/21/26
  • Parking Lot Rehabilitation Portion City Yard Rehabilitation Modernization
  • Chino Hills
  • $387,000
  • 4/16/26
  • Lone Hill Avenue Street Rehabilitation
  • Glendora
  • $1,828,000
  • 4/16/26
  • FY 25 26 Sunny Sands Neighborhood Cathedral Canyon Drive Pavement Rehabilitation
  • Cathedral City
  • $1,217,000
  • 4/10/26
  • FY 2025 26 Annual Major Streets Rehabilitation Program Madera Road Cochran Street Easy Street
  • Simi Valley
  • $453,000
  • 4/9/26
  • Raitt Street Protected Buffered Bike Lane Rehabilitation
  • Santa Ana
  • $8,882,000
  • 4/9/26
  • 4327 Almond Avenue Collins Avenue Street Improvements
  • Orange
  • $1,728,000
  • 4/9/26
  • McFadden Avenue Rehabilitation
  • Santa Ana
  • $1,962,950
  • 4/7/26
  • Firethorne Area Street Rehabilitation
  • Fullerton
  • $1,785,000
  • 4/7/26
  • Pacific Wanda Louise Walnut Area Street Rehabilitation
  • Fullerton
  • $588,000
  • 4/1/26
  • Cedarbrook Pavement Rehabilitation Between Glenwood Drive Aliso Viejo Parkway
  • Aliso Viejo
  • $888,000
  • 3/26/26
  • Palm Street Area Rehabilitation
  • Fullerton
  • $1,736,999
  • 3/26/26
  • First Avenue Rehabilitation
  • Arcadia
  • $1,428,000
  • 3/26/26
  • Aliso Viejo Parkway Pavement Rehabilitation Between Enterprise Aliso Creek Road
  • Aliso Viejo
  • $1,882,000
  • 3/25/26
  • Baker Avenue Rehabilitation
  • Fullerton
  • $596,000
  • 3/25/26
  • FY 24 25 Citywide Street Resurfacing
  • Stanton
  • $515,000
  • 3/25/26
  • FY 2025 26 Annual Major Streets Rehabilitation Program Tapo Canyon Rd Township Ave Avenida Simi
  • Simi Valley
  • $376,000
  • 3/24/26
  • Annual Alley Improvements FY25 26
  • Lynnwood
  • $535,700
  • 3/23/26
  • FY 2025 26 Street Improvements Program
  • Chino Hills
  • $1,888,000
  • 3/19/26
  • CDBG Alleyway Improvement
  • Montclair
  • $234,000
  • 3/19/26
  • Street Preservation Local Citywide FY 25 26 Worktag 68598
  • Pomona
  • $2,424,000
  • 3/16/26
  • ADA Sidewalk Improvements Community Development Block Grant CDBG
  • Pico Rivera
  • $242,000
  • 3/10/26
  • Industrial Street Repair Program
  • Santa Ana
  • $4,906,000
  • 3/5/26
  • Los Alisos Pavement Rehab
  • Rancho Santa Margarita
  • $479,000
  • 3/5/26
  • Santa Margarita Parkway Pavement Rehab
  • Rancho Santa Margarita
  • $987,000
  • 3/5/26
  • FY24 25 SR710 LATIP SB 1 Street Rehabilitation
  • Alhambra
  • $1,524,000
  • 3/5/26
  • On Call Street Rehabilitation Slurry Seal Contract
  • Irvine
  • $23,333,000
  • 3/5/26
  • Blake Street Other Roads Phase 1
  • San Bernardino County
  • $5,110,000
  • 3/5/26
  • 2025 26 Overlay A
  • Santa Clarita
  • $6,432,000
  • 3/3/26
  • 2026 Streets Overlay
  • El Centro
  • $3,536,000
  • 2/26/26
  • Business Area Road Improvements
  • Santa Ana
  • $1,028,000
  • 2/25/26
  • Citywide Pavement Repair Rehabilitation Program Phase 2 2025
  • Santee
  • $2,197,390
  • 2/24/26
  • FY 25 26 Street Rehabilitation
  • Duarte
  • $882,000
  • 2/23/26
  • Arterial Pavement Preservation Program S El Camino Real W Ave Gaviota W Ave San Antonio
  • San Clemente
  • $357,000
  • 2/19/26
  • FY 25 26 CDBG ADA Curb Ramps
  • Duarte
  • $117,000
  • 2/17/26
  • E Santa Fe Parking Lot Rehabilitation
  • Fullerton
  • $345,000
  • 2/12/26
  • Bella Canto Neighborhood Pavement Rehabilitation
  • Coachella
  • $483,000
  • 2/12/26
  • Street Pavement Repair Program FY 2025 26
  • Newport Beach
  • $1,082,000
  • 2/10/26
  • FY24 25 Residential Street Rehabilitation
  • West Covina
  • $3,282,000
  • 2/9/26
  • Montecito Drive Transit Access Improvements (REBID)
  • Chino Hills
  • $567,000
  • 2/5/26
  • FY 2026 As Needed Street Improvement Program Pavement Repairs
  • San Clemente
  • $432,000
  • 2/5/26
  • Civic Center Rehabilitation Bristol Shelton
  • Santa Ana
  • $423,000
  • 2/5/26
  • Whitewater Neighborhood Road Improvement Fiscal Year 2025 2026
  • Cathedral City
  • $794,538
  • 2/4/26
  • 2025 CDBG Residential Street Overlay
  • Westminster
  • $789,000
  • 2/3/26
  • FY 2025 26 Annual Minor Streets Rehabilitation Program Phase I Concrete SB1
  • Simi Valley
  • $1,020,000
  • 1/29/26
  • FY 2025 26 Annual Minor Streets Rehabilitation Program CDBG
  • Simi Valley
  • $848,000
  • 1/22/26
  • Commercial Street Improvement DInard Ave Maryton Ave Marquardt Ave Park Street Pike St
  • Santa Fe Springs
  • $2,142,000
  • 1/22/26
  • Alley Pavement Rehabilitation Program
  • San Clemente
  • $345,000
  • 1/22/26
  • West Glendale ADA Curb Ramp Installation Sidewalk Repair Program Phase 2
  • Glendale - CA
  • $6,369,000
  • 1/21/26
  • Grand Avenue Rehabilitation Edinger Avenue McFadden Avenue 23-6700
  • Santa Ana
  • $1,011,000
  • 1/9/26
  • FY 2026 Major Street Maintenance FY 2026 Pavement Preservation Program
  • San Clemente
  • $654,000
  • 1/8/26
  • Sidewalk Maintenance Program Phase II District I
  • Whittier
  • $1,069,000
  • 1/8/26
  • 2024 25 Citywide Slurry Seal CIP 2410
  • Hemet
  • $678,000
  • 1/7/26
  • Pavement Rehabilitation Auto Plaza Drive
  • Loma Linda
  • $369,000
  • 1/6/26
  • Citywide Sidewalk Repairs No PW 26 07
  • Oxnard
  • $1,234,000
  • 1/6/26
  • Asphalt Paving Maintenance Bike Trails Parking Lots
  • Irvine
  • $999,000
  • 1/6/26
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Carson
  • $8,878,000
  • 1/5/26
Bidjudge
CASH FLOW
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Norwalk
  • $4,636,000
  • 09/13/26
  • 120
  • 4.2%
  • $1,159,000
  • $4,442,833
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Fullerton
  • $622,000
  • 08/31/26
  • 70
  • 25.7%
  • $266,571
  • $462,057
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Fullerton
  • $1,414,000
  • 08/02/26
  • 120
  • 40.0%
  • $353,500
  • $848,400
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Agoura Hills
  • $1,007,000
  • 07/25/26
  • 120
  • 45.8%
  • $251,750
  • $545,458
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Artesia
  • $793,000
  • 07/20/26
  • 120
  • 50.0%
  • $198,250
  • $396,500
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Santa Ana
  • $3,369,000
  • 07/20/26
  • 85
  • 70.6%
  • $1,189,059
  • $990,882
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Fountain Valley
  • $2,317,000
  • 07/12/26
  • 120
  • 56.7%
  • $579,250
  • $1,004,033
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Oceanside
  • $9,669,000
  • 07/05/26
  • 120
  • 62.5%
  • $2,417,250
  • $3,625,875
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Simi Valley
  • $276,000
  • 07/04/26
  • 120
  • 63.3%
  • $69,000
  • $101,200
  • MLK JR Street Improvements Main Street Avalon Boulevard
  • Arcadia
  • $1,428,000
  • 05/25/26
  • 120
  • 96.7%
  • $357,000
  • $47,600
  • $6,840,630
  • $21,865,838
Bidjudge