- A Teichert & Son Teichert Const
- 2026
- 45
- 7
- 15.56%
- $143,579,348
- 15.91%
- 10.73%
- 5.66%
- $531,429,843

The **$160M** remaining backlog provides solid near-term support, anchored by the full **$20M** Roads Program award and active phases of multiple 2025-2026 projects. Cash inflows should remain steady given the long durations and partial remaining values on larger contracts. The **13.2%** 2026 success rate reflects disciplined bidding that sustains workload without overcommitment.
Medium-term Outlook (6-12 months)
Backlog conversion will draw from **$160M** total remaining, with meaningful contributions from the **$55M** Kings County and **$60M** Placer Parkway projects bid in early 2026. Annual award levels near **$141M** support replenishment if success rates stay above **13%**. Extended contract terms enable predictable but gradual revenue recognition through 2027.
Key Risk Period
The 2027-2028 window presents elevated risk as several 2024-2025 awards with 200-600 month durations approach completion, potentially creating gaps if new wins slow. Variable success rates (**10.7%-16.5%**) and high bid volumes amplify exposure to market or estimating shifts during this transition.
Recommendations
Target **$200M+** annual bid volume with focused pursuit of shorter-duration work to balance the long-term portfolio. Implement monthly backlog burn tracking and working-capital forecasting tied to the **$160M** remaining. Strengthen pre-bid qualification to lift success rates above **15%** and reduce concentration risk.
- Sacramento Last Mile Project Package 3 B27151111002
- Sacramento
- 9/23/26
- Pavement Installation Repair Services
- Santa Clara County
- 8/31/26
- 23 052 Roads Program CIP
- Turlock
- 7/28/26
- 06-0S37U4 Kings Fresno Counties Near Lemoore From 0.3 Mile South Excelsior Avenue 1.0 Mile South Co
- Caltrans
- 2/12/26
- Placer Parkway Phase 1 Construction
- Placer County
- 2/10/26
- 2025 CDBG Pavement Rehabilitation Project
- King City
- 2/5/26
- Citywide Street Reconstruction Phase 5
- San Mateo
- 2/5/26
- 06-0H22U4 Madera County Madera From San Joaquin River Bridge 0.6 Mile North Avenue 12 Overcrossing
- Caltrans
- $85,174,000
- 10/22/26
- Vasco Road Safety Improvements Phase 2 0662-6R4411
- Contra Costa County Public Works
- $22,737,099
- 9/24/26
- Sacramento Last Mile Project Package 3 B27151111002
- Sacramento
- $2,535,000
- 9/23/26
- Pavement Installation Repair Services
- Santa Clara County
- $80,454
- 8/31/26
- Salinas Municipal Airport Improvements FAA AIP No 03 06 0206 37
- Salinas
- $1,160,832
- 8/20/26
- 04-1W7104 Alameda County Fremont From 0.3 Mile North Scott Creek Road Undercrossing 1.0 Mile South
- Caltrans
- $3,456,437
- 8/18/26
- 05-1S5904 Monterey County At Various Locations
- Caltrans
- $4,211,323
- 8/11/26
- 23 052 Roads Program CIP
- Turlock
- $20,280,558
- 7/28/26
- 10-1K6204 Merced County Merced At Gerard Avenue
- Caltrans
- $3,977,473
- 7/16/26
- Mills Crossing Right Of Way Infrastructure
- Rancho Cordova
- $4,408,393
- 7/16/26
- Pavement Management 2026
- San Ramon
- $5,222,294
- 7/15/26
- 2026 Pavement Preservation
- San Mateo County
- $2,305,562
- 6/4/26
- 10-1M2304 San Joaquin County French Camp At Mathews Road Undercrossing
- Caltrans
- $7,106,444
- 6/2/26
- Abbott Street Sanitary Sewer Pavement Improvements
- Salinas
- $14,906,957
- 6/2/26
- City Fresno Pave More Now Bid Package B2
- Fresno
- $15,454,000
- 5/19/26
- Citywide Street Rehabilitation Package 6 B2
- San Mateo
- $3,132,702
- 5/14/26
- Citywide Road Surface Repair FY26
- Monterey
- $4,039,001
- 5/5/26
- 6B E Street Waterline Replacement 9th St Improvements
- Patterson
- $10,899,800
- 4/30/26
- FY26 Street Resurfacing
- Palo Alto
- $3,626,688
- 4/22/26
- AC Overlay 2026 Phase B
- Sacramento County
- $15,155,538
- 4/16/26
- 2026 Major Streets Resurfacing 2
- San Jose
- $8,520,305
- 4/16/26
- 03-3G6104 Yolo County At Zamora From 0.1 Mile South Adams Creek Bridge 0.2 Mile North Route 505/5 S
- Caltrans
- $5,619,814
- 4/14/26
- Fair Oaks Boulevard Bicycle Pedestrian Mobility Phase 2
- Sacramento County
- $9,689,776
- 4/9/26
- AC Overlay 2026 Phase A
- Sacramento County
- $12,664,172
- 4/9/26
- SJC New Taxiway Victor Phase 3A
- San Jose
- $13,802,400
- 4/9/26
- 2521 Slurry Seal Resurfacing Portions Various Roadways
- Alameda County
- $4,271,264
- 4/7/26
- 10-1S6304 Merced County Merced Livingston At Various Locations
- Caltrans
- $3,084,248
- 4/2/26
- 03-3G7504 Butte County At Butte Valley From Route 70 Separation 0.2 Mile South Durham Pentz Road Fr
- Caltrans
- $4,359,888
- 3/26/26
- 03-3G7804 Yuba County At Olivehurst From Route 65/70 Separation Yuba River Bridge
- Caltrans
- $3,662,824
- 3/25/26
- 10-1U0604 Stanislaus County Patterson From 1.1 Miles North Main Canal Bridge 0.2 Mile South Sperry
- Caltrans
- $3,828,400
- 3/18/26
- 10-1U0804 Merced County At Santa Nella From 0.1 Mile North Mccabe Road The Intersection Sullivan Ro
- Caltrans
- $3,717,037
- 3/17/26
- FY26 Pavement Improvement
- Alameda County
- $11,203,198
- 3/17/26
- 2026 DOT SLT Road Maintenance Pavement Rehabilitation
- El Dorado County
- $3,484,214
- 3/10/26
- 2043 Zone 7 Pavement Management Phase 1
- Pittsburg
- $3,590,351
- 2/26/26
- Grayson Walnut Creeks Levee Improvement CCCSD Treatment Plant
- Contra Costa County
- $8,312,882
- 2/17/26
- 2025 Pavement Maintenance Overlay WPR025
- Elk Grove
- $5,440,602
- 2/12/26
- 06-0S37U4 Kings Fresno Counties Near Lemoore From 0.3 Mile South Excelsior Avenue 1.0 Mile South Co
- Caltrans
- $54,562,400
- 2/12/26
- 10-1U0404 San Joaquin County Near Stockton From 0.3 Mile West Oro Avenue 0.9 Mile West Murray Road
- Caltrans
- $3,956,233
- 2/12/26
- Placer Parkway Phase 1 Construction
- Placer County
- $59,648,964
- 2/10/26
- 2025 CDBG Pavement Rehabilitation Project
- King City
- $2,197,060
- 2/5/26
- Citywide Street Reconstruction Phase 5
- San Mateo
- $4,274,912
- 2/5/26
- 06-1H9704 Madera County Near Chowchilla From Route 59/152 Separation 0.1 Mile West Route 99/152 S
- Caltrans
- $5,012,000
- 2/3/26
- Fresno Pave More Now Bid Package B 1
- Fresno
- $9,689,200
- 1/20/26
- 03-0J4004 El Dorado County Placerville From 0.1 Mile West Carson Road Overcrossing 5 Mile Road 1.0
- Caltrans
- $35,972,744
- 1/14/26
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $20,994,400
- 1/13/26
- Sacramento Last Mile Project Package 3 B27151111002
- Sacramento
- $2,535,000
- 11/22/26
- 80
- 0%
- -
- $2,535,000
- Pavement Installation Repair Services
- Santa Clara County
- $80,454
- 10/30/26
- 120
- 0%
- -
- $80,454
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Turlock
- $20,280,558
- 09/26/26
- 120
- 25.8%
- $5,070,140
- $15,041,414
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $54,562,400
- 04/13/26
- 585
- 33.7%
- $2,798,072
- $36,188,395
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Placer County
- $59,648,964
- 04/11/26
- 400
- 49.8%
- $4,473,672
- $29,973,604
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $29,830,200
- 02/16/26
- 380
- 66.6%
- $2,355,016
- $9,969,567
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $8,130,810
- 02/09/26
- 595
- 43.7%
- $409,957
- $4,577,851
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $14,122,511
- 01/18/26
- 605
- 46.6%
- $700,290
- $7,539,787
- 06-0Y1804 Madera County Madera From 0.1 Mile South Avenue 13 0.1 Mile South East Madera Underpas
- Caltrans
- $53,123,992
- 10/13/25
- 530
- 71.5%
- $3,007,018
- $15,135,326
- $18,814,165
- $121,041,398