- Fuller & Co
- 2026
- 6
- 3
- 50.00%
- $31,371,704
- 9.17%
- 5.35%
- 9.03%
- $42,430,984

Fuller & Co enters the period with **$26.6M** in remaining backlog across three long-duration projects, supporting steady but slow revenue drawdown given 120-month contracts. Bidding activity strengthened in 2026 with a 50% success rate and **$31.4M** in low bids, yet limited near-term starts constrain cash inflows. Focus remains on mobilizing the two FY27 awards totaling **$22.8M**.
Medium-term Outlook (6-12 months)
Execution of the **$26.6M** backlog will continue at a measured pace, with only **$3.9M** already recognized on the earliest project. Improved win rate and **$42.4M** in 2026 bids position the firm for potential backlog growth if conversion holds. Cash flow visibility improves only if additional shorter-cycle work is secured.
Key Risk Period
The extended 120-month durations on all active projects create prolonged cash flow exposure and working capital strain through 2027-2028. Low prior-year volume (**$9.8M** in 2025 lows) and thin 9.17% average left on low bids amplify sensitivity to delays or change-order disputes.
Recommendations
Prioritize bidding shorter-duration contracts to accelerate revenue recognition and diversify the pipeline. Implement monthly cash flow forecasting tied to the **$26.6M** backlog and maintain bid volume above 2026 levels to rebuild backlog.
- FY27 Water Main Replacement
- Charlotte
- $7,587,389
- 7/30/26
- FY27 Sanitary Sewer Rehabilitation
- Charlotte
- $6,954,098
- 7/29/26
- FY27 Water Sewer Infrastructure Construction Contract 1
- Charlotte
- $15,198,357
- 7/15/26
- Water System Replacement Phase 2
- High Shoals
- $1,178,673
- 7/7/26
- FY27 Water Main Replacement Contract 1
- Charlotte
- $2,926,509
- 5/12/26
- FY26 Small Diameter Water Sewer Services Contract 1
- Charlotte
- $8,585,958
- 4/8/26