- Summit Construction Development
- 2026
- 60
- 6
- 10.00%
- $77,163,875
- 2.00%
- 22.29%
- 9.45%
- $415,072,213

Summit enters the period with a solid **$92M** remaining backlog supported by multiple large awards in March-April 2026, including **$30.8M** and **$32.8M** projects. The improved **12%** success rate and **$77M** in 2026 low bids should generate steady cash inflows as mobilization begins on resurfacing and infrastructure work.
Medium-term Outlook (6-12 months)
Execution of the **$92M** backlog will continue to drive revenue, aided by the contractor’s shift to higher-value wins despite fewer bids. Sustained bidding activity at current volumes positions the firm for additional awards that could extend workload into 2027.
Key Risk Period
The 12-18 month window carries elevated risk as several 120-month contracts overlap, potentially stretching working capital and resources if change orders or delays materialize on the larger **$30M+** jobs.
Recommendations
Prioritize margin protection on active projects given the low **2%** average left on low bids; accelerate cash collections and limit new bid volume until backlog burn rate stabilizes.
- ADA Alpharetta Adult Activity Center Parking Lot Improvements
- Alpharetta
- 4/23/26
- 2026 01 2026 Resurfacing
- Lowndes County
- 4/21/26
- 26 32 Jonesboro Road
- Henry County
- 4/17/26
- B1CBA2601737-0 Cobb
- GDOT
- 4/17/26
- 2026 Resurfacing Phase 1 85708
- Cherokee County
- 4/6/26
- B1CBA2601181-0 Henry
- GDOT
- 3/20/26
- P I 0020661 SR 166 Chapel Hill Road
- Douglas County
- $1,529,759
- 7/24/26
- B3CBA2602464-0 Fulton
- GDOT
- $3,479,347
- 7/17/26
- B3CBA2602460-0 Fulton
- GDOT
- $6,056,136
- 7/17/26
- B3CBA2602311-0 Douglas
- GDOT
- $19,268,264
- 7/17/26
- B3CBA2602468-0 DeKalb
- GDOT
- $2,249,448
- 7/17/26
- B3CBA2602463-0 Cobb
- GDOT
- $2,126,275
- 7/17/26
- B3CBA2602320-0 Cherokee
- GDOT
- $65,463,318
- 7/17/26
- B1CBA2602337-0 Banks
- GDOT
- $4,976,711
- 7/17/26
- 27 001 FY27 Milling Resurfacing
- Alpharetta
- $4,619,640
- 7/16/26
- Peachtree Corners Circle Roundabout
- Peachtree City
- $1,683,130
- 6/15/26
- 26 39 Jonesboro Road Resurfacing I 75 Rosebud Lane
- Gwinnett County
- $3,697,550
- 6/12/26
- RFB 2026 02 LMIG Asphalt Resurfacing
- Holly Springs
- $533,898
- 6/5/26
- BL087 26 South Rockbridge Road Pedestrian Improvement
- Gwinnett County
- $4,255,650
- 6/4/26
- SR410 US78 CR 9476 Mountain Industrial Blvd Roadway Improvement
- Tucker
- $9,839,273
- 6/4/26
- FY 2026 LMIG Roadway Resurfacing
- Berrien County
- $1,883,209
- 5/28/26
- 2026 Resurfacing Pilgrim Mill Road
- Cumming
- $990,046
- 5/27/26
- Technology Parkway AV Lane Reconfiguration
- Peachtree Corners
- $1,288,365
- 5/19/26
- 2026 Roadway Resurfacing Patching Facilities Paving
- Johns Creek
- $1,883,209
- 5/15/26
- 26 008 2026 Road Resurfacing Improvements
- Flowery Branch
- $961,459
- 5/14/26
- Northstar Drive Kennedy Street Roundabout
- Columbus GA
- $846,282
- 5/13/26
- 2026 Resurfacing Phase 3 85708
- Cherokee County SC
- $4,548,286
- 5/8/26
- Due West SR 92 Realignment
- Paulding County
- $2,789,924
- 5/1/26
- ADA Alpharetta Adult Activity Center Parking Lot Improvements
- Alpharetta
- $262,350
- 4/23/26
- BL039 26 Eva Kennedy Road Water Main Replacement
- Gwinnett County
- $1,430,513
- 4/21/26
- 2026 01 2026 Resurfacing
- Lowndes County
- $5,657,031
- 4/21/26
- Patching Milling Resurfacing Various Douglas County Roads
- Douglas County
- $3,198,003
- 4/20/26
- B3CBA2601739-0 Gwinnett
- GDOT
- $7,641,843
- 4/17/26
- B1CBA2601766-0 Lumpkin
- GDOT
- $4,069,829
- 4/17/26
- B1CBA2601737-0 Cobb
- GDOT
- $1,814,443
- 4/17/26
- B1CBA2601741-0 Clayton
- GDOT
- $3,617,547
- 4/17/26
- 26 32 Jonesboro Road
- Henry County
- $30,887,789
- 4/17/26
- B1CBA2601706-0 Habersham
- GDOT
- $3,955,698
- 4/17/26
- Chapel Hill Road Widening Reconstruction
- Douglas County
- $8,385,794
- 4/17/26
- Sidewalk Construction Cumming Street Westside Parkway Devore Road
- Alpharetta
- $2,125,858
- 4/16/26
- Collins Industrial Way Traffic Safety Improvements
- Lawrenceville
- $1,392,900
- 4/7/26
- 2026 Resurfacing Phase 1 85708
- Cherokee County
- $5,657,031
- 4/6/26
- 2026 Resurfacing Phase 2 85708
- Cherokee County
- $4,539,551
- 4/6/26
- Construction Overflow Parking Lot Cauley Creek Park
- Johns Creek
- $571,805
- 4/2/26
- BL051 26 Lawrenceville Suwanee Rd Russell Rd Taylor Rd Dean Rd Winder Highway Hosea Rd Intersection
- Gwinnett County
- $1,111,976
- 3/26/26
- B1CBA2601539-0 Hall
- GDOT
- $3,190,617
- 3/20/26
- B1CBA2601541-0 Bartow
- GDOT
- $3,540,021
- 3/20/26
- B1CBA2601533-0 Butts/Monroe
- GDOT
- $6,996,271
- 3/20/26
- B1CBA2601181-0 Henry
- GDOT
- $32,885,231
- 3/20/26
- B3CBA2601542-0 Clayton/Fulton
- GDOT
- $4,129,662
- 3/20/26
- B1CBA2601527-0 Meriwether
- GDOT
- $4,424,719
- 3/20/26
- B1CBA2601532-0 Troup
- GDOT
- $6,491,631
- 3/20/26
- Forest Valley Water Main Replacement
- Gwinnett County
- $2,744,777
- 3/12/26
- Gwinnett Drive Widening
- Lawrenceville
- $897,033
- 3/3/26
- BL034 26 Oak Road Mountain View Road Intersection Improvement
- Gwinnett County
- $2,143,608
- 2/20/26
- B3CBA2601364-0 FORSYTH
- GDOT
- $680,959
- 2/20/26
- B1CBA2601365-0 DOUGLAS
- GDOT
- $4,387,061
- 2/20/26
- B1CBA2601413-0 PAULDING
- GDOT
- $4,766,136
- 2/20/26
- B3CBA2601360-0 GREENE
- GDOT
- $39,929,379
- 2/20/26
- 2026 SPLOST Milling Resurfacing Various Streets Districts 1 4
- Clayton County
- $9,719,644
- 2/19/26
- B2314 Holly Springs Road Davis Road
- Cobb County
- $999,650
- 2/12/26
- Nesbit Ferry Road Colony Club Drive Intersection Improvements
- Johns Creek
- $4,789,846
- 1/29/26
- B3CBA2601210-0 Barrow, Gwinnett, Hall
- GDOT
- $43,636,958
- 1/23/26
- PI 0017691 Resurfacing Eight 8 Streets
- Columbus
- $5,085,403
- 1/21/26
- East Cherokee Drive Macedonia Elementary School 82130
- Cherokee County
- $983,124
- 1/20/26
- Gulledge Road Creekview Way Improvement
- Paulding County
- $1,361,343
- 1/16/26
- Gulledge Road Creekview Way Improvement
- Alpharetta
- $262,350
- 06/22/26
- 120
- 37.5%
- $65,588
- $163,969
- Gulledge Road Creekview Way Improvement
- Lowndes County
- $5,657,031
- 06/20/26
- 180
- 26.1%
- $942,839
- $4,179,917
- Gulledge Road Creekview Way Improvement
- Henry County
- $30,887,789
- 06/16/26
- 120
- 41.7%
- $7,721,947
- $18,017,877
- Gulledge Road Creekview Way Improvement
- GDOT
- $1,814,443
- 06/16/26
- 120
- 41.7%
- $453,611
- $1,058,425
- Gulledge Road Creekview Way Improvement
- Cherokee County
- $5,657,031
- 06/05/26
- 120
- 51.7%
- $1,414,258
- $2,734,232
- Gulledge Road Creekview Way Improvement
- GDOT
- $32,885,231
- 05/19/26
- 730
- 10.7%
- $1,351,448
- $29,371,467
- $11,949,691
- $55,525,887